GB-Torpoint: Emergency Shutdown (ESD) Valves -
This is a contract result notice, not an open opportunity. Details from the official award data.
This sits below the typical range for Construction contracts — a smaller, more accessible award. Based on 64,002 valued Construction tenders in our corpus.
Outline Scope This project enables early works related to the Thanckes Overfill Protection Project.
Within the Overfill Protection Project, a new safety PLC exerts executive action over new ESD valves to prevent loss of containment of fuel.
The ESD valves will be ready for installation in piping line-work prior to the safety PLC being available so in order to proceed a solution is required to maintain plant operations.
This project enables temporary manual operation of each valve via a local switch.
What the notice asks for
The ESD valves will be ready
The ESD valves will be ready for installation in piping line-work prior to the safety PLC being available so in order to proceed a solution is required to maintain plant operations.
Sentences from the notice that state an obligation, surfaced automatically and shown in the order they appear. Not an exhaustive list — always confirm against the tender documents.
Make the case to bid
Reveal who to approach at Oil and Pipelines Agency, and generate a go-to-market strategy from their news, accounts and people.
Free to start. Named contacts come from published notices; the strategy is generated from the buyer’s news, accounts and people.
- OCID
- 10dab8d5-d6f9-4658-82b4-3927de43d21b
- Stage
- contract · Contract
- Source
- Contracts Finder
- Buyer ref
- BIP294096959
Contains public sector information licensed under the Open Government Licence v3.0. Source data © Crown copyright.
Who wins this kind of work
The suppliers and buyers around this opportunity — drawn from official award data. Drag to orbit; click a node to explore.
Top suppliers & buyers in Construction
Oil and Pipelines Agency’s tender network