Phase 1 Cladding Remedial Works Project - French, Finch and Margaret House
This opportunity relates to cladding works in relation to : French House: Introduction of compartmentation and removal of the HPL only (Existing combustible insulation and timber battens to remain).
Removal of the timber decking to the balconies and top terrace areas.
Finch & Margaret House: The existing failed cavity barriers are to be removed and new barriers are to be installed as per manufacturers recommendations at horizontal, vertical, window/door openings and service vents. • The High-Pressure Laminate (HLP) Cladding panels and combustible insulation are to be removed and replaced with a non-combustible alternative - (not required at Margaret House as no HPL). • The timber decking to the balcony attachments are to be removed and replaced with a non-combustible alternative • To Wall Types 2 & 3, the combustible insulation is to be removed and replaced with a non-combustible alternative, should it not be fire treated.
What the supplier must deliver
To Wall Types 2 & 3,
To Wall Types 2 & 3, the combustible insulation is to be removed and replaced with a non-combustible alternative, should it not be fire treated.
Derived from the notice text — always confirm against the original documents.
Make the case to bid
Reveal who to approach at Wandle Housing Association, and generate a go-to-market strategy from their news, accounts and people.
- OCID
- 3c1b2bb6-d2d8-42c6-b793-2c0240164c88
- Stage
- contract · Contract
- Source
- Contracts Finder
- Buyer ref
- BIP899300296
Contains public sector information licensed under the Open Government Licence v3.0. Source data © Crown copyright.
Who wins this kind of work
The suppliers and buyers around this opportunity — drawn from official award data. Drag to orbit; click a node to explore.
Top suppliers & buyers in Construction
Assembling the market network…
Wandle Housing Association’s tender network
Assembling the network…
Similar open tenders
Tender for Phase 1 River Restoration Works on Ballymartrim River supported by PEACEPLUS CALM
Armagh City, Banbridge and Craigavon Borough Council
Boston Leisure Project - Phase 2 MEP works
Boston Borough Council