RFP QuestBeta
ClosedStage · contract

Bedford College

Refurbishment and thermal upgrading works to the Halls of Residence at Shuttleworth College

ConstructionCPV 45000000
ValueValue not published
Deadline15 Jan 2024
Published13 Dec 2023
RegionNationwide
Timeline
Published 13 Dec 2023ClosedCloses 15 Jan 2024
Match for your company
Sign up free to see how well this tender matches your company — the score, the signals that align, and where the gaps are.
The brief

Bedford College is seeking a fixed price tender to carryout refurbishment works to five halls of residence and the linked common room at Shuttleworth College.

There are two residential blocks comprising of 80 rooms.

During the period 05/02/24 and 28/06/24; four of the five blocks plus the common room shall be occupied.

Until.

Work to the student residential blocks will be phased commencing with Patworth Hall.

The block will remain empty during the works.

Once work is completed, residents will relocate to Patworth Hall and work to Ongley Hall will commence.

Block 1 - Clayton & Edmunds.

Block 2 - Milner; Ongley & Patworth Block 1 was partially refurbished in the summer of 2013.

The bedrooms were stripped out and new loose/fixed furniture installed.

The electrical system was upgraded All blocks have had minor updating including the shower rooms.

The tender shall also include for providing site welfare and principal contractor duties for two other work packages [see Note 1 below]: • Flat roofing & insulation works to the following buildings - The two hall of residence blocks; common room; Russell Hall [excluding the sports hall] & the LRC/IT block. • District heating; new plant room works [adjacent to the ZEC] and heating updating [excluding the Halls of Residence].

Note 1 - all of the preliminaries associated with the work packages above [excluding the provision of welfare are excluded from this tender.

Note 2 - The roofing works are programmed to be carried out between 05/02/2024 and 21/06/2024. [20 weeks] Note 3 - The SALIX works [district heating; plant room and heating (excluding the Halls of Residence].

Works are planned to commence on 25/03/24 and be completed [including witnessing & commissioning by 30/09/24 [27 weeks] The main works to halls of residence are scheduled to commence on 05/02/24 and be fully completed for occupation by 30/08/24 [34 weeks].

Tender should include the following.

1) All of the works to the Halls of Residence and the common room.

See note 4 Note 4 - The tender for these works shall be submitted by the addition of two contract sum analysis cost schedules [SALIX and non-Salix works (excluding the works set out in note 1] 2) Provided site welfare and principal contraor support for the additional work packages set out in Note

Key requirements

What the supplier must deliver

01

During the period 05/02/24 and 28/06/24; four

During the period 05/02/24 and 28/06/24; four of the five blocks plus the common room shall be occupied.

02

The tender shall also include for providing

The tender shall also include for providing site welfare and principal contractor duties for two other work packages [see Note 1 below]:.

03

Tender should include the following

Tender should include the following.

04

The tender for these works shall

The tender for these works shall be submitted by the addition of two contract sum analysis cost schedules [SALIX and non-Salix works (excluding the works set out in note 1].

05

2) Provided site welfare and principal contraor

2) Provided site welfare and principal contraor support for the additional work packages set out in Note.

Derived from the notice text — always confirm against the original documents.

Buyer intelligence

Make the case to bid

Reveal who to approach at Bedford College, and generate a go-to-market strategy from their news, accounts and people.

Source & provenance
OCID
b40f5184-40fe-4e78-901c-0c469fcb70d4
Stage
contract · Contract
Source
Contracts Finder
Buyer ref
SALIXREFURBWORKS
View the original notice on Contracts Finder

Contains public sector information licensed under the Open Government Licence v3.0. Source data © Crown copyright.

Market context

Who wins this kind of work

The suppliers and buyers around this opportunity — drawn from official award data. Drag to orbit; click a node to explore.

Top suppliers & buyers in Construction

Assembling the market network…

Bedford College’s tender network

Assembling the network…

Also open now

Similar open tenders

Tresham Kettering Campus Heating & Hot Water Upgrade Project

Bedford College

Closes 20 Jul 2026Construction
£350kValue

CA18125 - Tresham Kettering Campus Heating & Hot Water Upgrade Project

Bedford College

Closes 20 Jul 2026Construction
£350kValue