BBV Sublot 4 - HSST1020 - Cut & Bent Steel Reinforcement - Curzon Approach Viaducts
This is a large award for Construction — above three-quarters of comparable contracts. Based on 64,002 valued Construction tenders in our corpus.
This scope is for the provision of cut and bent steel reinforcement for Curzon Approach Viaducts.
The supplier should review the steel reinforcement drawings and cut and bent steel in accordance with the drawings and bar bending schedules provided by the Contractor.
The bars should be cut and bent at the supplier's premises and comply with the relevant BBV/HS2 specification and relevant British Standards: • All hot rolled and cold worked steel bars shall conform to BS EN 10080 and BS 4449 Grades B500B or B500C • BS 8666 from 2005 and eventually 2020 Scheduling, dimensioning, bending and cutting of Steel Reinforcement for Concrete • The mandrel diameter for bending bars shall comply with Clause 8.3 of BS EN 1992-1-1. • CARES product acceptance scheme for steel reinforcement • Couplers shall be TA1A CARES certified The supplier should also provide any couplers including threading and any relating protection of the re-bars.
Bars should be delivered to site labelled with the references of the bar bending schedule and pre-slung to facilitate safe unloading.
Supplier should also provide any method statements and their related risk assessment as well as all relevant quality documentation such as quality management plan, grade mill certificates for the supplied re-bar, CARES certificates, CARS certificates and technical data sheets for the couplers, samples for testing (if required) and any other required to demonstrate compliance with the specification and industry standards.
The package covers three key activities spanning over the next 2 and half years.
These are the construction of the complex Curzon no.
3 post tensioned reinforced concrete deck and its finishes with 6220m3 of concrete and 2384tonnes of reinforcement remaining, the construction of the deck finishing works across the remaining assets of Curzon Approach (Curzon no.
2, Curzon no.
1 and Duddeston Viaduct) with ....tonnes remaining and the fabrication of the precast concrete slabs for Curzon Approach at BBV Kingsbury Yard with ....tonnes remaining.
What the supplier must deliver
The supplier should review the steel reinforcement
The supplier should review the steel reinforcement drawings and cut and bent steel in accordance with the drawings and bar bending schedules provided by the Contractor.
The bars should be cut and bent
The bars should be cut and bent at the supplier's premises and comply with the relevant BBV/HS2 specification and relevant British Standards:.
All hot rolled and cold worked steel
All hot rolled and cold worked steel bars shall conform to BS EN 10080 and BS 4449 Grades B500B or B500C.
The mandrel diameter for bending bars shall
The mandrel diameter for bending bars shall comply with Clause 8.3 of BS EN 1992-1-1.
Couplers shall be TA1A CARES certified
Couplers shall be TA1A CARES certified.
Derived from the notice text — always confirm against the original documents.
Make the case to bid
Reveal who to approach at Balfour Beatty VINCI JV HS2, and generate a go-to-market strategy from their news, accounts and people.
- OCID
- dd4927e0-8991-4aa8-9ea6-ecb6676e7d86
- Stage
- contract · Contract
- Source
- Contracts Finder
- Buyer ref
- C4N112415949
Contains public sector information licensed under the Open Government Licence v3.0. Source data © Crown copyright.
Who wins this kind of work
The suppliers and buyers around this opportunity — drawn from official award data. Drag to orbit; click a node to explore.
Top suppliers & buyers in Construction
Assembling the market network…
Balfour Beatty VINCI JV HS2’s tender network
Assembling the network…