RFP QuestBeta
ClosedStage · contract

Balfour Beatty VINCI Systra JV

WP15.04 IEP Access and Retaining Wall - Old Oak Common (S4) Station

Construction MaterialsCPV 44212400 71311100
Value£5.0m
Deadline25 Apr 2025
Published10 Apr 2025
RegionLondon
Timeline
Published 10 Apr 2025ClosedCloses 25 Apr 2025
Contract value in context
£5.0mtotal contract value
median £135k
this tender£0£5.4m

This is a large award for Construction Materials & Structures — above three-quarters of comparable contracts. Based on 10,341 valued Construction Materials & Structures tenders in our corpus.

Match for your company
Sign up free to see how well this tender matches your company — the score, the signals that align, and where the gaps are.
The brief

WP 15.04 IEP Access and Retaining wall Scope The scope consists of two key components: A new/altered access route at the west end of the Hitachi IEP Depot to facilitate construction works for the wider project.

A new retaining wall structure to retain the IEP Depot infrastructure whilst also forming the eastern boundary of the new Old Oak Common Lane alignment.

The following will be required: Detailed design, supply and installation of the above scope.

Fully coordinated design with the existing and new Old Oak Common Lane alignments, Part 2/3 bridge structure, utilities through Old Oak Common Lane and the GWML UTX tunnels.

Provide RIBA 5 design and construction drawings including setting out detailing, general arrangements, and elevation drawings for construction.

Provide samples and construct a mock up in accordance with the Old Oak Common Lane Schedule 17 architectural requirements IEP Depot Access Route (Stage 2) - the ramp The existing access route in the southwest corner of the Hitachi IEP Depot needs adapting to suit Old Oak Common (BBVS and SRSA) construction traffic requirements.

IEP Depot Retaining Wall Construction of a new bored piled retaining wall supporting the embankment to the south west corner of the IEP Depot.

Piling, plunge columns, concrete planks, masonry finish, backfilling, RC concrete Could separate our piling/plunge columns from other works Piling could be incorporated into the highways scope Utility diversions to enable works above Several existing utilities running through the IEP Depot will need to be diverted or managed before major civils and excavation works can commence.

These include: Foul sewer Multiple LV electricity supplies Telecoms

Key requirements

What the supplier must deliver

01

Detailed design, supply and installation of

Detailed design, supply and installation of the above scope.

02

Provide RIBA 5 design and construction drawings

Provide RIBA 5 design and construction drawings including setting out detailing, general arrangements, and elevation drawings for construction.

03

Provide samples and construct a mock up

Provide samples and construct a mock up in accordance with the Old Oak Common Lane Schedule 17 architectural requirements.

04

Several existing utilities running through the IEP

Several existing utilities running through the IEP Depot will need to be diverted or managed before major civils and excavation works can commence.

Derived from the notice text — always confirm against the original documents.

Buyer intelligence

Make the case to bid

Reveal who to approach at Balfour Beatty VINCI Systra JV, and generate a go-to-market strategy from their news, accounts and people.

Source & provenance
OCID
e7f64e8b-2281-4640-aa83-3b5e885bae83
Stage
contract · Contract
Source
Contracts Finder
Buyer ref
C4N92697960
View the original notice on Contracts Finder

Contains public sector information licensed under the Open Government Licence v3.0. Source data © Crown copyright.

Market context

Who wins this kind of work

The suppliers and buyers around this opportunity — drawn from official award data. Drag to orbit; click a node to explore.

Top suppliers & buyers in Construction Materials & Structures

Assembling the market network…

Balfour Beatty VINCI Systra JV’s tender network

Assembling the network…

Also open now

Similar open tenders

Manufacture and supply of Culvert & Wing Walls for Leicestershire County Council

Leicestershire County Council

Closes 27 Jul 2026Construction Materials
£80kValue

Supply & Fit Mobile access gantries

Thameslink Southern Great Northern Limited (TSGN)

Closes 31 Aug 2026Construction Materials
£550kValue