GB-Edinburgh: Refurbishment of DGPS Masts - Earls Hill
This is a contract result notice, not an open opportunity. Details from the official award data.
This sits in the lower-middle of the Construction Materials & Structures band — a mid-scale opportunity. Based on 10,341 valued Construction Materials & Structures tenders in our corpus.
The following gives an outline description of the works: Stage 1 - Carry out a conditional survey of each mast including all fixings, connections, guys ropes and anchorage point and then report on the suitability of the masts in their current condition.
Stage 2 - Disconnect top antenna wires running between all three masts.
This work must be undertaken by a competent nominated antenna contractor.
The removal of the antenna wires shall allow NLB Staff to undertake tuning tests to establish whether the station can be run using only the central mast.
The outcome of the works at this stage shall determine the scope and timescales for further works, there are three possible options as listed: Option 1 Should the trials prove unsuccessful the antenna wires shall be re-connected and then stage 3a of the works shall be implemented.
Option 2 Should the trials show a strong indication that using only the central mast will be successful the refurbishment/demolition works shall be delayed for 4 weeks to allow NLB personnel to monitor the results.
After this period Stage 3b of the works will be implemented as advised by NLB Rep.
Option 3 Should the trials prove inconclusive the NLB retain the option to extend the trial period to 6 months after which time the works will move on to either stage 3a or 3b as determined by NLB Rep.
All tenderers should take note of the above and price in accordance particularly in relation to mobilisation of site.
Stage 3a - Refurbishment of all three masts as detailed in the Bill of Quantities.
Stage 3b - Refurbishment of the central mast only with the outer masts being taken down and removed from site as outline in the Bill of Quantities.
Stage 4 - Demobilisation and site clearance Site visits will be conducted on Wednesday 3 August 2016 for this project.
Please contact Ruth Millan, Procurement@nlb.org.uk to confirm attendance.
What the supplier must deliver
This work must be undertaken by
This work must be undertaken by a competent nominated antenna contractor.
The removal of the antenna wires shall
The removal of the antenna wires shall allow NLB Staff to undertake tuning tests to establish whether the station can be run using only the central mast.
The outcome of the works at this
The outcome of the works at this stage shall determine the scope and timescales for further works, there are three possible options as listed:.
Should the trials prove unsuccessful the antenna
Should the trials prove unsuccessful the antenna wires shall be re-connected and then stage 3a of the works shall be implemented.
Should the trials show a strong indication
Should the trials show a strong indication that using only the central mast will be successful the refurbishment/demolition works shall be delayed for 4 weeks to allow NLB personnel to monitor the results.
Derived from the notice text — always confirm against the original documents.
Make the case to bid
Reveal who to approach at Northern Lighthouse Board, and generate a go-to-market strategy from their news, accounts and people.
Ask me about this tender, the buyer, who wins their work, or whether you should bid.
- OCID
- 6e097ea2-e4b7-4930-9dd4-25bc501239ee
- Stage
- contract · Contract
- Source
- Contracts Finder
- Buyer ref
- BIP224724644
Contains public sector information licensed under the Open Government Licence v3.0. Source data © Crown copyright.
Who wins this kind of work
The suppliers and buyers around this opportunity — drawn from official award data. Drag to orbit; click a node to explore.
Top suppliers & buyers in Construction Materials & Structures
Northern Lighthouse Board’s tender network
Assembling the network…
Similar open tenders
Request for Quotation for INTERNAL REFURBISHMENT WORKS AT RESIDENTIAL DWELLINGS
West Oxfordshire District Council
London and Quadrant Housing Trust - Mast Hire Dynamic Purchasing System (DPS)
London and Quadrant Housing Trust