Heating, Ventilation & Comfort Cooling Improvements At The Saxilby Close Boxing Club

ConstructionCPV 45000000 45300000 45330000
Value£55,000
Awarded15 Jan 2021
Published9 Dec 2020
RegionEast Midlands

£55,000 — stated in the notice.

Outcome — awarded

This is a contract result notice, not an open opportunity. Details from the official award data.

Contract value in context
£55ktotal contract value
median £158k
this tender£0£6.5m

This sits in the lower-middle of the Construction band — a mid-scale opportunity. Based on 64,002 valued Construction tenders in our corpus.

The brief

The Council is seeking a suitably qualified, experienced and accredited Contractor to complete the detailed design, supply, installation and commissioning of improved heating, ventilation and comfort cooling systems at the Saxilby Close Boxing Club to improve the facility's internal environment.

This project will see the replacement of the existing, outdated and ineffective mechanical extraction system in the Gymnasium and the standalone extractor fans in the Changing Rooms, with a modern supply & extract heat recovery ventilation system and a central extract system respectively.

The redundant blown warm air heating unit is to be removed, with the existing air conditioning installation improved and expanded to provide cost effective heating / comfort cooling, using simplified "user friendly" controls.

Changing rooms will also benefit from electric radiant heaters, providing instantaneous heat as required.

The Works shall include the removal and appropriate disposal offsite of all redundant equipment and all associated building work / making good for a "turn-key" project.

As well as commissioning and certifying the new installations, the Contractor shall obtain a Building Regulation Completion Certificate and procure a new Energy Performance Certificate appropriate for the facility.

The Works shall include full End User & Maintenance Training and a Maintenance Contract for the first 12 months from Completion.

The Contract must be completed no later than Wednesday 31st March 2021.

Requirements

What the notice asks for

01

This project will see the replacement

This project will see the replacement of the existing, outdated and ineffective mechanical extraction system in the Gymnasium and the standalone extractor fans in the Changing Rooms, with a modern supply & extract heat recovery ventilation system and a central extract system respectively.

02

The redundant blown warm air heating unit

The redundant blown warm air heating unit is to be removed, with the existing air conditioning installation improved and expanded to provide cost effective heating / comfort cooling, using simplified "user friendly" controls.

03

The Works shall include the removal

The Works shall include the removal and appropriate disposal offsite of all redundant equipment and all associated building work / making good for a "turn-key" project.

04

As well as commissioning and certifying

As well as commissioning and certifying the new installations, the Contractor shall obtain a Building Regulation Completion Certificate and procure a new Energy Performance Certificate appropriate for the facility.

05

The Works shall include full End User

The Works shall include full End User & Maintenance Training and a Maintenance Contract for the first 12 months from Completion.

Sentences from the notice that state an obligation, surfaced automatically and shown in the order they appear. Not an exhaustive list — always confirm against the tender documents.

The gates

What this notice demands of you

1 named in obligation language, 0 mentioned. Each one is quoted from the notice.

EPC (energy performance certificate)says mustCertification & assessment schemes
As well as commissioning and certifying the new installations, the Contractor shall obtain a Building Regulation Completion Certificate and procure a new Energy Performance Certificate appropriate for the facility.

Matched against the notice text, so this is a floor — the tender pack will demand things the notice never mentions. “Says must” means the quoted sentence itself used obligation language; anything ambiguous is left as a mention.

Buyer intelligence

Make the case to bid

Reveal who to approach at CORBY BOROUGH COUNCIL, and generate a go-to-market strategy from their news, accounts and people.

Sign up free to unlock buyer intelligence

Free to start. Named contacts come from published notices; the strategy is generated from the buyer’s news, accounts and people.

Source & provenance
OCID
45aa6d9e-af1a-4cb5-afb0-f888395c7472
Stage
contract · Contract
Source
Contracts Finder
Buyer ref
CBCHVCCSCBC2020
View the original notice on Contracts Finder

Contains public sector information licensed under the Open Government Licence v3.0. Source data © Crown copyright.

Market context

Who wins this kind of work

The suppliers and buyers around this opportunity — drawn from official award data. Drag to orbit; click a node to explore.

Top suppliers & buyers in Construction

This view needs WebGL, which this browser has turned off.

CORBY BOROUGH COUNCIL’s tender network

This view needs WebGL, which this browser has turned off.
Also open now

Similar open tenders

Dartford Football Club Roof Cladding Works

Dartford Borough Council

Closes 12 Oct 2026Construction
£1,300,000Value

RESPONSE MAINTENANCE AND IMPROVEMENT WORKS

Northern Ireland Housing Executive

Closes 12 Oct 2026Construction
£95,931,041Value