United Kingdom Atomic Energy Authority
Alternative Measurement Methods
This is a contract result notice, not an open opportunity. Details from the official award data.
This sits in the upper-middle of the Research & Development band — a substantial contract for the sector. Based on 20,405 valued Research & Development tenders in our corpus.
Working with the STEP programme, the Control Systems Integration (CSI) work area is looking to support these ambitions by developing its knowledge of the necessary plant control systems and potential requirements of a Fusion Power Plant (FPP).
As part of this, there is significant challenge in providing the necessary sensors for the control and monitoring of the plasma relevant aspects of the power plant.
This specifically relates to the sensors and associated equipment required to operate within the harsh environment in and around the fusion machine (tokamak) itself.
With the greatest risk being around the ability to provide the necessary measurements within a radiative environment.
Given that the greatest challenge will be in the measurement systems being able to meet performance requirements under irradiation, the identification of alternative ways to measure the required parameters is of interest to the STEP Programme.
Measurement systems undergo performance losses and eventual failure under irradiation which results in the inability to meet the requirements of control systems functions - both safety and commercial.
A traditional solution for overcoming challenges to radiation is to develop radiation hard technologies.
For applications to a fusion power plant, there is a concern that the development of a radiation tolerant/hard technology will not be enough, and so alternative approaches should be considered.
This work should aim to identify novel approaches and solutions to this problem - it is essential a solution is found to enable commercial viability of fusion energy power plants.
What the supplier must deliver
Working with the STEP programme, the Control
Working with the STEP programme, the Control Systems Integration (CSI) work area is looking to support these ambitions by developing its knowledge of the necessary plant control systems and potential requirements of a Fusion Power Plant (FPP).
This specifically relates to the sensors
This specifically relates to the sensors and associated equipment required to operate within the harsh environment in and around the fusion machine (tokamak) itself.
With the greatest risk being around
With the greatest risk being around the ability to provide the necessary measurements within a radiative environment.
Given that the greatest challenge will
Given that the greatest challenge will be in the measurement systems being able to meet performance requirements under irradiation, the identification of alternative ways to measure the required parameters is of interest to the STEP Programme.
For applications to a fusion power plant
For applications to a fusion power plant, there is a concern that the development of a radiation tolerant/hard technology will not be enough, and so alternative approaches should be considered.
Derived from the notice text — always confirm against the original documents.
Make the case to bid
Reveal who to approach at United Kingdom Atomic Energy Authority, and generate a go-to-market strategy from their news, accounts and people.
Ask me about this tender, the buyer, who wins their work, or whether you should bid.
- OCID
- 1dc51d5a-777e-4272-a46e-793e82306316
- Stage
- contract · Contract
- Source
- Contracts Finder
- Buyer ref
- 20230426172351-72814
Contains public sector information licensed under the Open Government Licence v3.0. Source data © Crown copyright.
Who wins this kind of work
The suppliers and buyers around this opportunity — drawn from official award data. Drag to orbit; click a node to explore.
Top suppliers & buyers in Research & Development
United Kingdom Atomic Energy Authority’s tender network
Assembling the network…