Sizewell C - HR Monitoring (CRX & Building) Package
This is a large award for Engineering & Architecture — above three-quarters of comparable contracts. Based on 33,646 valued Engineering & Architecture tenders in our corpus.
Overview of Scope Supply and installation of the HR Monitoring System to the to CRX and Nuclear Island Building The EAU (containment monitoring) system is required to continuously monitor and assess the mechanical behaviour and integrity of the Reactor Building and integrity of the Reactor Building and associated at nuclear island at Sizewell C (SZC) throughout construction, testing, and operation.
The system scope covers the design, supply, installation, commissioning, and documentation of: • Monitoring sensors (including extensometers, temperature probes, hydraulic levelling pots, pendulums, invar wires, inclinometers, hygrometers, and pressure sensors) • Associated cabling, connection/grouping boxes, and acquisition/data logger cabinets • All necessary software interfaces and data collection/reporting tools More than 200 sensors will be embedded and installed in both the inner containment wall and the common raft of the nuclear island.
The EAU monitoring system must provide real-time and periodic data on: • Settlements and deformations of the nuclear island raft (topographical markers, hydraulic levelling pots, extensometers, and temperature sensors) • Overall containment distortions (pendulums and invar wires) • Localized deformations and tendon failure detection (embedded extensometers, local monitoring devices) • Tension in prestressed cables (dynamometers) • Environmental parameters (temperature, humidity, internal and external pressure) All EAU system components must comply with the Book of Technical Specifications (BTS) Chapter 9.04 and associated referenced as well as client installation and interface requirements.
Instruments must be delivered with calibration certificates and installed in accordance with manufacturer and project-specific procedures.
The EAU system contractor will also provide: • Installation studies and execution drawings for all phases (temporary/erection and permanent/operational) • Material Approval Forms, Inspection and Test Plans, Quality Release Certificates, and Lifetime Quality Records (LTQR) • Data collection, reporting formats, and periodic analysis files as required by the client (monthly/bi-monthly during construction; weekly/daily during key phases; and as specified during operation)
What the supplier must deliver
Supply and installation of the HR Monitoring
Supply and installation of the HR Monitoring System to the to CRX and Nuclear Island Building.
The EAU (containment monitoring) system is required
The EAU (containment monitoring) system is required to continuously monitor and assess the mechanical behaviour and integrity of the Reactor Building and integrity of the Reactor Building and associated at nuclear island at Sizewell C (SZC) throughout construction, testing, and operation.
The system scope covers the design, supply
The system scope covers the design, supply, installation, commissioning, and documentation of:.
The EAU monitoring system must provide real-time
The EAU monitoring system must provide real-time and periodic data on:.
All EAU system components must comply
All EAU system components must comply with the Book of Technical Specifications (BTS) Chapter 9.04 and associated referenced as well as client installation and interface requirements.
Derived from the notice text — always confirm against the original documents.
Make the case to bid
Reveal who to approach at Sizewell C Limited, and generate a go-to-market strategy from their news, accounts and people.
- OCID
- 5ec0fb87-1fe6-492f-9a9a-20cfb71fb2dc
- Stage
- contract · Contract
- Source
- Contracts Finder
- Buyer ref
- C4N108307220
Contains public sector information licensed under the Open Government Licence v3.0. Source data © Crown copyright.
Who wins this kind of work
The suppliers and buyers around this opportunity — drawn from official award data. Drag to orbit; click a node to explore.
Top suppliers & buyers in Engineering & Architecture
Assembling the market network…
Sizewell C Limited’s tender network
Assembling the network…