Extension of Tarmac Path with Lights at Merriman Park, Street, Somerset

Engineering & ArchitectureCPV 71000000
ValueValue not published
Awarded23 Oct 2016
Published12 Sept 2016
RegionSouth West
Outcome — awarded

This is a contract result notice, not an open opportunity. Details from the official award data.

The brief

PATHWAY WILL BE EXTENDED IN ACCORDANCE WITH SCALE PLAN MPK/PWY/0816 (ATTACHED) AND RUN FROM EXISTING PATH TO PEDESTRIAN GATE NEAR THE SILVER ROAD/PARK ROAD JUNCTION.

SURFACING TARMAC WILL BE LAID TO SAME SPECIFICATION AS EXISTING (SEE GUIDANCE PROVIDED BELOW) AND PROVISION OF LIGHTS TO THE SAME SPECIFICATION AS EXISTING.

THE LANTERNS ARE CHURCHILL LANTERNS DL70S FITTED WITH 70w SODIUM LAMPS AND PHOTOCELLS.

THEY WILL BE POSITIONED ALONG THE NEW PATHWAY AT SIMILAR DISTANCES AS EXISTING LIGHTS AND SPECIFIC LOCATIONS ARE INDICATED ON DRAWING MPK/PWY/0816.

NOTE ON TARMAC PATH – FOOTWAY EXTENSION TO BE 1.5M WIDE, LAID IN ACCORDANCE WITH SOMERSET COUNTY COUNCIL – ESTATE ROADS IN SOMERSET SPECIFICATION CONSTRUCTION NOTES (GREEN BOOK) APPENDICES F AND M – SEE LINK BELOW http://www.somerset.gov.uk/policies-and-plans/strategies/somerset-highway-infrastructure/ IN ACCORDANCE WITH THE BRITISH STANDARD FOR TREES IN RELATION TO DESIGN, DEMOLITION AND CONSTRUCTION (BS 5837 : 2012), NO MACHINERY CAN BE USED WITHIN THE ROOT PROTECTION AREA (RPA) OF TREES.

TO ENSURE THEIR PROTECTION, EXCAVATION WILL BE CARRIED OUT BY HAND UNDERNEATH ALL TREE CANOPIES AND WITHIN ALL ROOT PROTECTION AREAS.

THE RPA OF A PARTICULAR TREE HAS BEEN INDICATED ON MPK/SUR/0916 REV2.

A DECISION HAS BEEN MADE NOT TO EXCAVATE AT ALL WITHIN THIS AREA.

INSTEAD, THE GROUND WILL BE BUILT UP USING 75mm CELLWEB TRP CONFINEMENT SYSTEM, PROVIDED BY GEOSYNTHETICS LTD.

THIS IS FILLED WITH CLEAN, ANGULAR STONE.

THE APPOINTED CONTRACTOR WILL LAY TARMAC ONTOP IIDEALLY PERMEABLE) OF THE CELLWEB AND GRAVEL BASE (PLEASE SEE 3X CELLWEB DOCUMENTS ATTACHED FOR FURTHER INFORMATION AND CONSTRUCTION DETAIL).

EXCESS SOIL FROM OTHER EXCAVATIONS WILL THEN BE USED TO CREATE A GENTLE SLOPE BETWEEN EXISTING GRASS AND THE FINISHED LEVEL OF THE NEW (CELL WEB) PATH.

IT WILL THEN BE FINISHED WITH NEW TURF THAT MUST BE WATERED IN.

NB: THE 75MM CELLWEB HAS A MAXIMUM GROSS WEIGHT CAPABILITY OF JUST 1 TONNE.

FOR THE DURATION OF WORKS, HERASS FENCING MUST BE ERECTED TO PROTECT AND SEPARATE EXISTING TREES FROM CONSTRUCTION WORK.

CONTRACTOR MUST EITHER PUT DOWN A TEMPORARY ROAD FOR VEHICLES OR MAKE GOOD ANY DAMAGE TO THE GROUND WHEN WORKS ARE COMPLETED.

PLANS OF SERVICES IN THE PARK WILL BE PROVIDED TO THE SUCCESSFUL CONTRACTOR BUT A CAT SCAN MUST ALSO BE CARRIED OUT PRIOR TO COMMENCEMENT OF WORKS.

PROVIDE A QUOTATION BY 12 NOON ON MONDAY, 24TH OCTOBER, 2016 TO THE CLERK, STREET PARISH COUNCIL, 6 LEIGH ROAD, STREET, SOMERSET BA16 0HA IN A CLEARLY MARKED ENVELOPE PROVIDE DETAILS OF TIMESCALES FOR COMPLETION OF WORKS COMPANIES MUST HAVE EMPLOYER AND PUBLIC LIABILITY INSURANCE OF £5 MILLION OR ABOVE AND PROVIDE WRITTEN CONFIRMATION OF THIS WITH A RISK ASSESSMENT METHOD STATEMENT PRIOR TO COMMENCEMENT OF WORKS THE COUNCIL IS NOT OBLIGED TO ACCEPT THE LOWEST OR ANY QUOTATION. prospective CONTRACTORS ARE PROHIBITED FROM CONTACTING COUNCILLORS OR STAFF.

Key requirements

What the supplier must deliver

01

TO ENSURE THEIR PROTECTION, EXCAVATION WILL

TO ENSURE THEIR PROTECTION, EXCAVATION WILL BE CARRIED OUT BY HAND UNDERNEATH ALL TREE CANOPIES AND WITHIN ALL ROOT PROTECTION AREAS.

02

IT WILL THEN BE FINISHED WITH NEW

IT WILL THEN BE FINISHED WITH NEW TURF THAT MUST BE WATERED IN.

03

FOR THE DURATION OF WORKS, HERASS FENCING

FOR THE DURATION OF WORKS, HERASS FENCING MUST BE ERECTED TO PROTECT AND SEPARATE EXISTING TREES FROM CONSTRUCTION WORK.

04

CONTRACTOR MUST EITHER PUT DOWN A TEMPORARY

CONTRACTOR MUST EITHER PUT DOWN A TEMPORARY ROAD FOR VEHICLES OR MAKE GOOD ANY DAMAGE TO THE GROUND WHEN WORKS ARE COMPLETED.

05

PLANS OF SERVICES IN THE PARK

PLANS OF SERVICES IN THE PARK WILL BE PROVIDED TO THE SUCCESSFUL CONTRACTOR BUT A CAT SCAN MUST ALSO BE CARRIED OUT PRIOR TO COMMENCEMENT OF WORKS.

Derived from the notice text — always confirm against the original documents.

The gates

What this notice demands of you

1 named in obligation language, 1 mentioned. Each one is quoted from the notice.

Employers' / public liability insurancesays mustFinancial standing & cover
COMPANIES MUST HAVE EMPLOYER AND PUBLIC LIABILITY INSURANCE OF £5 MILLION OR ABOVE AND PROVIDE WRITTEN CONFIRMATION OF THIS WITH A RISK ASSESSMENT METHOD STATEMENT PRIOR TO COMMENCEMENT OF WORKS
IN ACCORDANCE WITH THE BRITISH STANDARD FOR TREES IN RELATION TO DESIGN, DEMOLITION AND CONSTRUCTION (BS 5837 : 2012), NO MACHINERY CAN BE USED WITHIN THE ROOT PROTECTION AREA (RPA) OF TREES.

Matched against the notice text, so this is a floor — the tender pack will demand things the notice never mentions. “Says must” means the quoted sentence itself used obligation language; anything ambiguous is left as a mention.

Buyer intelligence

Make the case to bid

Reveal who to approach at Street Parish Council, and generate a go-to-market strategy from their news, accounts and people.

Source & provenance
OCID
5e589ac5-dd05-404e-91a3-ef0af212a29b
Stage
contract · Contract
Source
Contracts Finder
Buyer ref
Path Extension with Lights
View the original notice on Contracts Finder

Contains public sector information licensed under the Open Government Licence v3.0. Source data © Crown copyright.

Market context

Who wins this kind of work

The suppliers and buyers around this opportunity — drawn from official award data. Drag to orbit; click a node to explore.

Top suppliers & buyers in Engineering & Architecture

Scroll to explore the market network

Street Parish Council’s tender network

Assembling the network…

Also open now

Similar open tenders

Reading Crematorium and Henley Rd Cemetery - 2025 Cemetery Extension -Consultant

Reading Borough Council

Closes 28 Aug 2026Engineering & Architecture
£300kValue

School Streets PM (ESPO Framework Agreement (reference 664-25)

Bath and North East Somerset Council

Closes 17 Oct 2026Engineering & Architecture
Value not publishedValue