RFP QuestBeta
Awarded · ResultStage · contract

Mace Dragados

HS2 Euston Station - Site Wide Logistics Package

ConstructionCPV 45000000 45100000 45110000
Value£5.0m
Awarded15 Dec 2020
Published9 Sept 2021
RegionUK-wide
Outcome — awarded

This is a contract result notice, not an open opportunity. Details from the official award data.

Contract value in context
£5.0mtotal contract value
median £158k
this tender£0£6.5m

This is a large award for Construction — above three-quarters of comparable contracts. Based on 64,002 valued Construction tenders in our corpus.

The brief

Mace Dragados are seeking expressions of interest from Subcontractors to undertake the full Site Wide Logistics Package.

The scope of the package consists of but is not limited to the following services/works: 1.

Logistics Management (including deliveries to site) 2.

Management of all vehicle movements to and from the Project from the point of site access to the point of site egress.

3.

Provision of a Site Wide experienced and competent Logistics Manager 4.

Provision of Site Equipment 5.

General Traffic Management 6.

Provision and management of minor civil/builders work 7.

Radio Communications 8.

Pedestrian Walkways, Barriers, Site Signage and Handrails 9.

Provision of Fire Marshalls, Fire Points and Extinguishers 10.

Operating the Delivery Management system 11.

Interface with Security Subcontractor 12.

Waste Management Works shall be contracted under NEC3 Engineering Construction Subcontract terms and conditions (with project specific amendments) Suppliers must have extensive demonstrable experience of delivering similar complex packages on previous projects of a similar scale on large major infrastructure projects.

This experience must be applicable and relevant to the respective lots listed.

If successful selected suppliers will be required to go through Mace Dragados pre-qualification process to be included on the final tender list.

Mace Dragados have been appointed as the Construction Partner to build a fully-integrated HS2 station at London Euston, together with links to the existing London Underground station.

HS2 Phase One includes construction of a new railway line run from London Euston to new stations at Old Oak Common in West London, an Interchange Station near Birmingham Airport and the National Exhibition Centre (NEC) and a terminus station in Birmingham City Centre (Curzon Street).

Key requirements

What the supplier must deliver

01

Works shall be contracted under NEC3 Engineering

Works shall be contracted under NEC3 Engineering Construction Subcontract terms and conditions (with project specific amendments).

02

Suppliers must have extensive demonstrable experience

Suppliers must have extensive demonstrable experience of delivering similar complex packages on previous projects of a similar scale on large major infrastructure projects.

03

This experience must be applicable and relevant

This experience must be applicable and relevant to the respective lots listed.

04

If successful selected suppliers will be required

If successful selected suppliers will be required to go through Mace Dragados pre-qualification process to be included on the final tender list.

05

Mace Dragados have been appointed as

Mace Dragados have been appointed as the Construction Partner to build a fully-integrated HS2 station at London Euston, together with links to the existing London Underground station.

Derived from the notice text — always confirm against the original documents.

Buyer intelligence

Make the case to bid

Reveal who to approach at Mace Dragados, and generate a go-to-market strategy from their news, accounts and people.

Source & provenance
OCID
465d69f7-a779-4a7b-8429-bd443c14a95f
Stage
contract · Contract
Source
Contracts Finder
Buyer ref
C4A52483442
View the original notice on Contracts Finder

Contains public sector information licensed under the Open Government Licence v3.0. Source data © Crown copyright.

Market context

Who wins this kind of work

The suppliers and buyers around this opportunity — drawn from official award data. Drag to orbit; click a node to explore.

Top suppliers & buyers in Construction

Scroll to explore the market network

Mace Dragados’s tender network

Assembling the network…

Also open now

Similar open tenders

Station Painting & Platform Lining Framework

Northern Trains Limited

Closes 24 Aug 2026Construction
£18.0mValue

26-E-STAN06-FOC08-INTERFLEX- West Tofts Camp-INTERFLEX Remediation (Work Package 5 - Roof Winterisation)

Ministry of Defence

Closes 21 Aug 2026Construction
Value not publishedValue