Kidlington Waste Removal Support Services
This is a contract result notice, not an open opportunity. Details from the official award data.
This is a large award for Engineering & Architecture — above three-quarters of comparable contracts. Based on 33,646 valued Engineering & Architecture tenders in our corpus.
This contract has been directly awarded via the Crown Commercial Services Agreement RM6165 Construction Professional Services, Lot 1, using the NEC4 PSC Option E contract form.
The call off has been made through a compliant route under the framework, with the urgency of the situation informing the decision to proceed by direct award.
The requirement arises from the identification of a significant fire risk at the Kidlington waste site by Oxfordshire Fire and Rescue Service.
A fire at this location would pose serious risks to public safety, including impacts on air quality, disruption to critical infrastructure such as the A34, and wider environmental harm.
This PSC contract provides the specialist project support needed to enable and oversee the associated NEC4 ECC contract for the full end to end clearance of approximately 21,000 tonnes of illegally deposited mixed waste.
The PSC is therefore essential to ensure the ECC can be delivered safely, compliantly and in a coordinated manner.
The PSC provides a specialist project support team for the Kidlington Waste Removal project, comprising: NEC4 ECC Project Manager, Cost Manager, NEC4 ECC Supervisor, Environmental Clerk of Works.
The forecast cost for these services is £458,163.11, based on the estimated level of resource required to support the project.
Under the NEC4 PSC Option E cost reimbursable model, and any changes to the forecast cost or contract duration are managed through the compensation event process set out in the contract.
Adjustments will only occur where compensation events are assessed and agreed in accordance with the contract conditions.
The PSC will run to 18.12.27 to allow sufficient time for any ECC programme elongation and the 12 month ECC defects period.
The PSC can be extended further if required to accommodate any additional delays or programme changes.
What the supplier must deliver
This PSC contract provides the specialist project
This PSC contract provides the specialist project support needed to enable and oversee the associated NEC4 ECC contract for the full end to end clearance of approximately 21,000 tonnes of illegally deposited mixed waste.
The PSC is therefore essential to ensure
The PSC is therefore essential to ensure the ECC can be delivered safely, compliantly and in a coordinated manner.
The PSC provides a specialist project support
The PSC provides a specialist project support team for the Kidlington Waste Removal project, comprising:.
The forecast cost for these services is
The forecast cost for these services is £458,163.11, based on the estimated level of resource required to support the project.
The PSC can be extended further if
The PSC can be extended further if required to accommodate any additional delays or programme changes.
Derived from the notice text — always confirm against the original documents.
Make the case to bid
Reveal who to approach at Environment Agency, and generate a go-to-market strategy from their news, accounts and people.
Ask me about this tender, the buyer, who wins their work, or whether you should bid.
- OCID
- 04eb7ab2-b8a7-4575-abe7-b696e02cbf24
- Stage
- contract · Contract
- Source
- Contracts Finder
- Buyer ref
- CF-0599400D8d000003VQwdEAG
Contains public sector information licensed under the Open Government Licence v3.0. Source data © Crown copyright.
Who wins this kind of work
The suppliers and buyers around this opportunity — drawn from official award data. Drag to orbit; click a node to explore.
Top suppliers & buyers in Engineering & Architecture
Environment Agency’s tender network
Assembling the network…