RFP QuestBeta
ClosedStage · tender

Lee Valley Heat Network Operating Company Limited, trading as Energetik

Energetik Primary Heating Network Extensions Part 2 (PSDS)

ConstructionCPV 45232140
Value£12.0m
Deadline6 May 2026
Published19 Mar 2026
RegionNationwide
Timeline
Published 19 Mar 2026ClosedCloses 6 May 2026
Who to contact
alina.caro@enfield.gov.uk

The procurement contact named on the official notice.

How to submit
Open the submissions portal

https://londonboroughofenfield.my.site.com Suppliers will need to register an interest on Atamis and submit a tender submission no later than 12:00 Noon on 6th May 2026 to participate and registration is free. Tender submissions cannot be uploaded after the return deadline.

The submission route named on the official notice.

Contract value in context
£12.0mtotal contract value
median £158k
this tender£0£13.0m

This is a large award for Construction — above three-quarters of comparable contracts. Based on 64,002 valued Construction tenders in our corpus.

Match for your company
Sign up free to see how well this tender matches your company — the score, the signals that align, and where the gaps are.
The brief

Energetik is seeking to extend its Meridian Water Heat Network (MWHN) in two separate parts, known as the northern extension and western extension.

The Employer will appoint a Contractor to design and build the pipe network.

The western extension is from Church Street near Edmonton Green to Winchmore School and Edmonton County (Bury Campus) School.

The northern extension is from Ponders End High Street near Ponders End Park to Capital College and Waverley School.

The contract is a district heating pipe installation of approximately 2.4km trench length of DN200 Series 3 pipe and 1.5km trench length of DN150 Series 3 pipe, all installed with at least 800mm cover to the crown of the pipe.

The majority of the pipe has been purchased by the Employer from Logstor and is being stored at Logstor, Denmark.

Works include being responsible for calling off the delivery of the pipe from Logstor, purchasing all joints and associated materials from Logstor, and installing the pipe predominantly in roads or cycle paths.

The pre-construction work for the contract is due to commence upon contract award on or before 30th June 2026.

As well normal pre-construction work required under the contract, further GPR work, design and trial holes will be permitted as part of preconstruction.

Construction work is expected to commence on or before 1st October 2026 following a successful planning application by the Employer, and subject to the Contractor agreeing S50 licences with Enfield Highways.

As the project is grant funded and the grant will be lost if the contract spend does not achieve certain minimum thresholds each financial year, the contract has a sectional completion date of 31st March 2027 and Practical Completion by 31st March 2028.

At least £4m of contract cost must be achieved by 31st March 2027, the sectional completion date.

Completion of contract works must be delivered by 31st March 2028.

Note that liquidated damages are £20,000 per day if these dates are not achieved.

Key to the success of the project is the liaison with Enfield Highways team and to develop a route design and traffic management proposals that permit the granting of Section 50 licences for the works.

Note that Section 50 licence fees, deposits and bonds will be paid by the Employer to Enfield Highways.

Full road closures are highly unlikely to be permitted, and multiple gangs will only be permitted where it does not cause undue traffic chaos to commuter sand businesses on Enfield’s roads.

The Contractor will be invited to meet Enfield Highways during the tender period.

The contract includes extending the existing Logstor leak detection system, cleaning the pipe installed, hydraulically testing the pipe installed using treated water to the same standard as the existing MWHN and commissioning of the extensions to provide “heat on” to the extended network.

The duration of the Contract is expected to be 21 months without option to extend due to completion of contract works must be delivered by 31st March 2028.

Please refer to the Procurement Documentation for more information.

Key requirements

What the supplier must deliver

01

Works include being responsible for calling off

Works include being responsible for calling off the delivery of the pipe from Logstor, purchasing all joints and associated materials from Logstor, and installing the pipe predominantly in roads or cycle paths.

02

Construction work is expected to commence on

Construction work is expected to commence on or before 1st October 2026 following a successful planning application by the Employer, and subject to the Contractor agreeing S50 licences with Enfield Highways.

03

At least £4m of contract cost must

At least £4m of contract cost must be achieved by 31st March 2027, the sectional completion date.

04

Completion of contract works must be delivered

Completion of contract works must be delivered by 31st March 2028.

05

The contract includes extending the existing Logstor

The contract includes extending the existing Logstor leak detection system, cleaning the pipe installed, hydraulically testing the pipe installed using treated water to the same standard as the existing MWHN and commissioning of the extensions to provide “heat on” to the extended network.

Derived from the notice text — always confirm against the original documents.

Buyer intelligence

Make the case to bid

Reveal who to approach at Lee Valley Heat Network Operating Company Limited, trading as Energetik, and generate a go-to-market strategy from their news, accounts and people.

Deep dive · beta

The full intelligence dossier

Our agent reads Lee Valley Heat Network Operating Company Limited, trading as Energetik’s accounts, hunts live signals, finds the people who decide — and hands you a bid strategy plus a go-to-market influence plan, including what your team should post this week. You approve every paid step.

Source & provenance
OCID
ocds-h6vhtk-066f44
Stage
tender · Open
Source
Find a Tender
Buyer ref
025310-2026
View the original notice on Find a Tender

Contains public sector information licensed under the Open Government Licence v3.0. Source data © Crown copyright.

Market context

Who wins this kind of work

The suppliers and buyers around this opportunity — drawn from official award data. Drag to orbit; click a node to explore.

Top suppliers & buyers in Construction

Scroll to explore the market network

Lee Valley Heat Network Operating Company Limited, trading as Energetik’s tender network

Assembling the network…

Also open now

Similar open tenders

Q1531 - Provision of Low Carbon Heating Upgrade at Ysgol Cynwyd Sant Primary School

Bridgend County Borough Council

Closes 10 Aug 2026Construction
£145kValue

Disabled Extension Works at 2 Fallowfield Close, Bradford, BD4 6LE

City of Bradford Metropolitan District Council

Closes 17 Aug 2026Construction