Operation Watershed - King George V Playing Field
This is a contract result notice, not an open opportunity. Details from the official award data.
The procurement contact named on the official notice.
The works involve implementing drainage improvements based on an approved scope of works, which has been agreed upon by MSDC, WSCC, and the Operation Watershed team.
The detailed specifications are attached: a.
Watercourse Link Plan b.
Drainage Construction Details A large part of this work will take place on the privately owned land of Cedar Cottage and Landis.
The quote should include making good of any area that is impacted by the works.
This will include replacing ship lap fencing and laying turf, as detailed on the plan.
The quote should include satisfying the conditions set in the Ordinary Watercourse Consent.
The following will apply: 1.
The warranty for the design will be held by GTA Civils.
2.
Before construction commences, test pit/trial holes will be dug to verify the building foundations reach the minimum requirements.
The contractor should allow for this in the quote.
3.
Works will be overseen by GTA Civils, and the contractor will be required to work with GTA Civils to accommodate three site visits to allow inspection of the work.
The contractor should allow for this in the quote.
4.
The construction of the pipe running alongside the property must be in accordance with Building Regulations Approved Document H.
What the supplier must deliver
The quote should include making good
The quote should include making good of any area that is impacted by the works.
The quote should include satisfying the conditions
The quote should include satisfying the conditions set in the Ordinary Watercourse Consent.
The contractor should allow for this in
The contractor should allow for this in the quote.
Works will be overseen by GTA Civils
Works will be overseen by GTA Civils, and the contractor will be required to work with GTA Civils to accommodate three site visits to allow inspection of the work.
The construction of the pipe running alongside
The construction of the pipe running alongside the property must be in accordance with Building Regulations Approved Document H.
Derived from the notice text — always confirm against the original documents.
Make the case to bid
Reveal who to approach at Worth Parish Council, and generate a go-to-market strategy from their news, accounts and people.
Ask me about this tender, the buyer, who wins their work, or whether you should bid.
- OCID
- ocds-h6vhtk-069eeb
- Stage
- award · Awarded
- Source
- Find a Tender
- Buyer ref
- 046986-2026
Contains public sector information licensed under the Open Government Licence v3.0. Source data © Crown copyright.
Who wins this kind of work
The suppliers and buyers around this opportunity — drawn from official award data. Drag to orbit; click a node to explore.
Worth Parish Council’s tender network
Assembling the network…