Bournemouth Beach Management Groyne Building Programme 2017-2019

Historical · ContractNo open deadline

Historical: no longer open for bids.

01/ The notice

Key facts

Value
£2,282,069Estimated value stated in the notice
Deadline (UK time)
Mon 7 Aug 2017A deadline does not apply to this historical notice. The source records Mon 7 Aug 2017, which is not an open deadline.
Published
13 Oct 2017
Region
South West

02/ The brief

What the notice says

Not fully read: this is the notice text; attached documents are not read.

Bournemouth Borough Council is seeking to appoint a contractor to construct an employer designed scheme comprising of the construction 12 (twelve) new timber groynes and the deconstruction of 12 (twelve) existing timber groynes.

The construction works are part of a long-term project to renew coastal defences at the Bournemouth seafront and will provide ongoing coastal protection of assets and property from coastal erosion and damage.

Due to the exposed nature of the site, the Contractor must ensure that sufficient resources are available to him at all times in order that he can complete the Works by the completion date using safe and reliable methods, experienced resources and effective management procedures

The construction sequencing is given below.

Phase 1 (16th October 2017 to 29th April 2018) - Works to commence no sooner than 16th October 2017 with sectional completion date of 29th April 2018 to construct 6 (six) new groynes (C51, C52, C53, C54, C55 & C56)and to deconstruct 6 (six) existing groynes numbered (B45, B46, B47, B48, B49 & B50) as shown on drawing number BBM-GRP-07, timber to be supplied by Bournemouth Borough Council

Phase 2a (1st October 2018 to 24th February 2019) - Works to commence no sooner than 1st October2018 with completion date of 24th February 2019 to construct 3 (three) new groynes (C48, C49 & C50) and deconstruct 3 (three) existing groynes (B42, B43 & B44), timber to be supplied by Bournemouth Borough Council

Phase 2b (1st October 2018 to 28th April 2019) - Works to commence no sooner than 1st October 2018 with completion date of 28th April 2019 to construct 3 (three) new groynes (C45, C46 & C47) and deconstruct 3(three) existing groynes (B39, B40 & B41)., timber to be supplied by Bournemouth Borough Council

The contract commences on Monday 16 October 2017 and works are to be completed by Sunday 28 April 2019.

A notice was sent to the European Journal regarding this opportunity on 28/06/2017.

03/ Classification

CPV codes

Common Procurement Vocabulary codes, exactly as the notice lists them. No descriptions are added here.

  • 45000000 45200000 45240000 71000000
  • 45000000 45240000 45243000 71000000

04/ History

Releases of this notice

One release held, oldest first. Dates are UK time.

  1. 13 Oct 2017
    Contract notice

    Contract notice published 13 October 2017.

    Release 0abaeca4-8ed6-4bc6-baee-88107143030c

    View this release on Contracts Finder (opens in a new tab)

05/ Limits

What the source does not tell us

  • Only one release is held, so there is no change history.

06/ Questions

About this notice

The Council of the Borough of Bournemouth published this notice.

Estimated value stated in the notice: £2,282,069.

08/ Related

Where to go next

These links follow a fixed rule applied to this notice’s buyer, text and CPV codes. They are not advice on whether to bid.

Reference
0abaeca4-8ed6-4bc6-baee-88107143030c
Source
Contracts Finder
Stage
contract · Contract
Last verified
Tue 7 Apr 2026, 19:46 BST
Read at
Fri 23 Oct 2026, 07:31 BST

Contains public sector information licensed under the Open Government Licence v3.0. Source data © Crown copyright.

RFP Quest logo — RFP software, RFP platform and RFP tools

Built on published notices from Find a Tender and Contracts Finder.

15 minutes · RFP Quest

Book a Demo