Contracts Finder · Historical
Weymouth & Portland Borough Council
Weymouth Harbour Quay Wall D - Strengthening Works
Historical: no longer open for bids.
01/ The notice
Key facts
- Value
- £588,847Estimated value stated in the notice
- Deadline (UK time)
- Mon 6 Aug 2018A deadline does not apply to this historical notice. The source records Mon 6 Aug 2018, which is not an open deadline.
- Published
- 1 Mar 2019
- Region
- South West
02/ The brief
What the notice says
Not fully read: this is the notice text; attached documents are not read.
Harbour Wall D is a 76 metre stretch of steel sheet piling harbour quay wall at the eastern end of Custom House Quay, Weymouth. The approximate centre point of the Wall D is 368268, 78824 (national grid reference). The works are in close proximity to grade 2* listed buildings (Devonshire Buildings) which are hotels and B&B's, and the Weymouth Pavilion theatre. Due to their close proximity, there will be a requirement for surveying and monitoring of the buildings by a third party. Contractors familiar with these arrangements and that can offer good communication and liaison with stakeholders will be most suited to this project.
The works comprise the construction of 76 metres of steel sheet pile quay wall driven into the harbour bed (to approximately -12 mCD) as close as practical to the face of the existing piles (approximately 0.5m offset). The void between existing and new will be filled with reinforced concrete and the new sheet piling will be tied back to the sound sections of the existing tie bars so that the strengthened wall will be supported by the existing anchor beams. The structure will be topped with a capping beam. These structural elements will combine the existing and new sheet piling and create a strengthened and supported harbour quay wall.
The Contractor must be competent in isolating underground services for the construction period and reinstating services on operation and completion.
A brick and concrete kiosk building (approximately 60m² and 3m tall) on the quayside will be demolished and replaced by a much smaller structure for electrical switchgear, built into the walls retaining the elevated section of landing stage.
The works includes provision of quay safety equipment and mooring bollards as appropriate, the removal of four flights of steel ferry steps and replacement with two new flights of reinforced concrete steps and the reinstatement of quayside furniture.
The quayside, working areas and contractor's compound will be made good on completion, using like-for-like materials to the existing.
The form of contract will be ECC Option C target contract. The contract is programmed to commence in January 2019. The duration of the contract is expected to be up to 20 weeks (lead in time dependant) including approximately 12 weeks of site works.
Advert Link (Supplying South West)
https://procontract.due-north.com/Advert?advertId=343133d4-5383-e811-80ed-005056b64545&p=696a9836-1895-e511-8105-000c29c9ba21
03/ Classification
CPV codes
Common Procurement Vocabulary codes, exactly as the notice lists them. No descriptions are added here.
- 45241100 45243600
- 45000000 45200000 45240000 45241000 45243000
04/ History
Releases of this notice
One release held, oldest first. Dates are UK time.
- 1 Mar 2019Contract notice
Contract notice published 1 March 2019.
Release 1dfba3df-5374-4726-93eb-d27414dca548
View this release on Contracts Finder (opens in a new tab)
05/ Limits
What the source does not tell us
- Only one release is held, so there is no change history.
06/ Questions
About this notice
07/ Tender hubs
More marine works tenders like this
This notice is closed and kept here as a record. These pages list the live notices in the same subject, buyer or place. Chosen by a fixed rule on the notice’s title, buyer and region.
Open now in Marine works tenders
- Canvey Lake DredgingCastle Point Borough Council · Published 1 Oct 2026Castle Point Borough Council are seeking to appoint a suitably experienced contractor to undertake dredging works at Canvey Lake, Canvey Island, Essex. Castle Point Borough Council has prioritised improvements to Canvey Lake following it taking back the management of the lake in July 2026. A total b£1,000,000Estimated value stated in the noticeCloses Mon 2 Nov 2026, 12:00 GMT
- Kishorn Port - Phase 1B - East Quay DevelopmentKishorn Port Limited · Published 2 Oct 2026Kishorn Port Limited (KPL) own and operate the drydock facility at Kishorn. The existing drydock has been enlarged with the rock material blasted and removed to reclaim 8.5 hectares of foreshore land to the east of the drydock. The contractor will construct a new 150m long quay at the newly formed£30,000,000Estimated value stated in the noticeCloses Mon 2 Nov 2026, 12:00 GMT
08/ Related
Where to go next
These links follow a fixed rule applied to this notice’s buyer, text and CPV codes. They are not advice on whether to bid.
- Reference
- 1dfba3df-5374-4726-93eb-d27414dca548
- Source
- Contracts Finder
- Stage
- contract · Contract
- Last verified
- Sat 11 Apr 2026, 14:31 BST
- Read at
- Fri 23 Oct 2026, 10:21 BST
Contains public sector information licensed under the Open Government Licence v3.0. Source data © Crown copyright.
Built on published notices from Find a Tender and Contracts Finder.