UK supplier guide
Public Contracts Regulations 2015:
when PCR still applies
The Public Contracts Regulations 2015 (PCR 2015) were revoked by the Procurement Act 2023, but they still govern every procurement commenced before 24 February 2025 and every contract, framework and dynamic purchasing system awarded under them, until those end.
Search current UK tenders →Checked against primary sources5 sources linked below
- Read the notice's legal basis
- Find when it commenced
- Use that regime's documents
- Check the arrangement's life
Date of commencement decides
Before 24 February 2025 means PCR 2015, for the life of the contract.Nearly a fifth of the record
12,704 of the year’s Find a Tender records cite the PCR directive.
Does PCR 2015 or the Procurement Act apply to this tender?
The date the procurement was commenced decides it, not the date you see the notice.
A public procurement in England, Wales or Northern Ireland
Commenced before 24 February 2025
PCR 2015 applies, including to the contract, any framework call-offs and any modification, until the contract or arrangement ends (Cabinet Office guidance, paras 4 to 6).
Notices follow the old rules too: a PCR modification is published under PCR, not as a contract change notice under the Act.
Commenced on or after 24 February 2025
The Procurement Act 2023 applies. Expect the procurement specific questionnaire, the central digital platform and the competitive flexible procedure.
What counts as “commenced” under PCR 2015?
Publishing a call for competition, or contacting a supplier to start a direct award, before 24 February 2025.
| Before 24 February 2025 the buyer had… | Rule |
|---|---|
| Awarded the contract, concluded the framework agreement or established the DPS | SI 2024/716, reg 5(3)(a) |
| Submitted a contract notice for publication | reg 5(3)(c) |
| Published a below-threshold opportunity on Contracts Finder | reg 5(3)(e) |
| Contacted a supplier to start a negotiated procedure without prior publication (PCR reg 32) | reg 5(3)(b) |
| Published a voluntary transparency notice of its intention to award | reg 5(3)(d) |
How do you work out which rules a tender is under?
Read the legal basis and the commencement date before the documents.
- Start with the source01
Read the notice's legal basis
2023/54 is the Act; Directive 2014/24/EU means PCR 2015. - Define the scope02
Find when it commenced
A contract notice or supplier contact before 24 February 2025 means PCR. - Read the evidence03
Use that regime's documents
The SQ under PCR, the PSQ and platform under the Act. - Make the decision04
Check the arrangement's life
PCR frameworks run to their last call-off; PCR DPSs end by 23 February 2029. - Name the next action05
Follow that regime's remedies and notices
Changes and notices follow the regime the contract was awarded under.
A supplier’s review sequence, based on the primary sources below. It is not a measured outcome or a prescribed buyer timetable.
How much of the market still runs under PCR 2015?
Nearly one Find a Tender record in five in the last twelve months cited the 2014 directive that PCR 2015 implements.
| Find a Tender records, by legal basis | 1 Oct 2025 to 30 Sep 2026 | September 2026 |
|---|---|---|
| Procurement Act 2023 | 57,505 | 6,642 |
| PCR 2015 (Directive 2014/24/EU) | 12,704 | 1,236 |
| of which awards and award updates | 9,793 | — |
| of which tenders and tender updates | 2,143 | — |
| of which planning notices | 768 | — |
When do PCR frameworks and DPSs finally end?
A PCR framework lasts until its last call-off ends; every PCR DPS ends by 23 February 2029.
A framework agreement set up under PCR keeps running under PCR until the last contract awarded under it ends (guidance, para 6c).
A PCR dynamic purchasing system’s validity could not be changed after 23 February 2026 and expires, if it has not already, at the end of 23 February 2029 (reg 5(4)(b)).
PCR 2015 applies
Procedures commenced before this date stayed under the 2006 rules (PCR reg 118).Procurement Act in force
New procurements run under the Act; PCR is revoked but saved.DPS terms frozen
A PCR DPS’s period of validity may not be changed after this date.Last PCR DPS ends
Any PCR DPS still running expires at the end of this day.
Which PCR 2015 procedures will you still meet?
Five competitive procedures and the negotiated procedure without prior publication, in place of the Act’s two.
PCR procedures
Negotiation and dialogue
Competitive procedure with negotiation and competitive dialogue, only where reg 26(4) allows (regs 29 and 30).
- Anyone may tender, or the buyer shortlists first (regs 27 and 28).
- Competitive procedure with negotiation and competitive dialogue, only where reg 26(4) allows (regs 29 and 30).
- Available under reg 26(3)(b) and regulated by reg 31.
- A direct award in the cases reg 32 lists, with no call for competition.
Read the legal basis on the notice before you read anything else.
Date of commencement decides
Before 24 February 2025 means PCR 2015, for the life of the contract.Nearly a fifth of the record
12,704 of the year’s Find a Tender records cite the PCR directive.DPSs end in 2029
Every PCR DPS expires by the end of 23 February 2029.
Free search across Find a Tender and Contracts Finder; open the notice to see which rules it was published under.
What else should you know about Public Contracts Regulations 2015?
Check these points before committing your team’s time.
Has the Public Contracts Regulations 2015 been repealed?
How do I tell whether a tender is under PCR 2015 or the Procurement Act?
Can a PCR framework still award call-offs in 2026?
Which rules govern changes to a PCR contract?
Does PCR 2015 still require payment within 30 days?
Where can you check the evidence?
Read the primary publication and the buyer’s current documents before acting.
| Source | What it supports |
|---|---|
| The Public Contracts Regulations 2015 (SI 2015/102) · legislation.gov.uk ↗ | Contents, procedures and transitional provision, read 24 October 2026. |
| PCR 2015 regulation 26, choice of procedures ↗ | Procedures available and when negotiation is allowed. |
| SI 2024/716 regulation 5 · legislation.gov.uk ↗ | What keeps PCR 2015 alive, and the DPS end dates. |
| Guidance: transitional and saving arrangements · Cabinet Office ↗ | What counts as commenced; contract management and notices. |
| Procurement Act 2023 · legislation.gov.uk ↗ | Revocation by section 119 and Schedule 11. |