Tender evaluation:
how the most advantageous tender wins
Tender evaluation is how a buyer scores the tenders it receives against the award criteria it published. Under the Procurement Act 2023 it may award to the supplier with the most advantageous tender, which is not the same as the cheapest.
Search UK tenders →Checked against primary sources4 sources linked below
- Conditions of participation
- Pass/fail criteria
- Weighted criteria
- Abnormally low price check
What is the most advantageous tender?
The tender that satisfies the buyer’s requirements and best satisfies the award criteria, assessed by the published method and weighting.
A contracting authority may award a public contract to the supplier that submits the most advantageous tender (s.19(1)).
That is the tender it considers “satisfies the contracting authority’s requirements” and “best satisfies the award criteria” when assessed by its assessment methodology and the relative importance of the criteria (s.19(2)).
- As described in the tender notice and associated documents.
- Set under section 23 and published in advance.
- How tenders are assessed, including any pass/fail criterion.
- Weighting, ranking or another description.
What rules apply to award criteria?
They must relate to the subject-matter, be clear, measurable and specific, follow the technical-specification rules and be proportionate.
| Section 23(2): the buyer must be satisfied the criteria… | What it means for your response |
|---|---|
| relate to the subject-matter of the contract | Answer what is being bought, how and when it is supplied, the staff who make a difference, and price or value |
| are sufficiently clear, measurable and specific | Mirror the wording and evidence each criterion asks for |
| do not break the rules on technical specifications in section 56 | Equivalent solutions should be assessable |
| are a proportionate means of assessing tenders | Expect lighter assessment on smaller, simpler contracts |
How is a tender scored?
Against published criteria, by a published method and weighting.
- Start with the source01
Conditions of participation
Fail them and the tender is disregarded. - Define the scope02
Pass/fail criteria
The methodology says which ones disqualify. - Read the evidence03
Weighted criteria
Quality, price and social value, by published importance. - Make the decision04
Abnormally low price check
You get a chance to explain before it is disregarded. - Name the next action05
Assessment summary
Your scores and the winner's, before the award notice.
A supplier’s review sequence, based on the primary sources below. It is not a measured outcome or a prescribed buyer timetable.
When can a buyer disregard a tender?
It must disregard a supplier that fails the conditions of participation, and may disregard an abnormally low price or a procedural breach.
- Before you start01
Use the current documents
Check the primary publication and later changes before using the sequence below. - Check 202
Conditions of participation
A tender from a supplier that does not satisfy them must be disregarded (s.19(3)(a)). Conditions must be proportionate and allow equivalent qualifications (s.22(4)–(5)). - Check 303
Abnormally low price
The buyer may disregard it, but must first tell you and give you a reasonable opportunity to show you can perform at that price (s.19(3)(c), (4)). - Check 404
Procedural requirement
Breaching a procedural requirement in the notice or documents, including failing to provide requested information, can lose the tender (s.19(3)(d), (11)). - Follow through05
Non-treaty suppliers
A tender from a supplier that is neither a UK nor a treaty state supplier may be disregarded (s.19(3)(b)).
An editorial order of work, not a buyer's fixed timetable. The current notice and documents determine participation and submission.
How much weight do UK buyers give price?
In Procurement Act tender notices with exact percentage weights, the median price weight was 40%; half sat between 30% and 60%.
| Price weight in the first lot’s criteria | Tender-stage records |
|---|---|
| 100% (price only) | 150 |
| 50–99% | 1,034 |
| 30–49% | 1,478 |
| 1–29% | 468 |
| All records with a price criterion and weights totalling 100% | 3,130 |
| Median price weight | 40% |
| Middle half of price weights | 30% to 60% |
What do you learn after evaluation?
An assessment summary of your tender and of the most advantageous tender, before the contract award notice.
Before publishing a contract award notice after a competition, the buyer must give each supplier whose tender was assessed an assessment summary (s.50(3)).
It covers the buyer’s assessment of your tender and, if different, of the most advantageous tender (s.50(4)). Then the standstill period runs.
- How it was assessed against each criterion.
- How the most advantageous tender was assessed.
- Disregarded tenders do not get one.
- The award notice starts the standstill.
Read the weighting before writing a word: it tells you where the marks are.
Most advantageous
Best against the published criteria, not lowest price.Weights are published
Percentage, ranking or another description.Price at 40%
The median exact weight in a year of Act tender notices.
Free: open notices with their buyer, deadline and published award criteria where the notice gives them.
What else should you know about tender evaluation?
Check these points before committing your team’s time.
What is the most advantageous tender?
Does the cheapest tender win?
Must a buyer publish its evaluation weightings?
What is an abnormally low tender?
Can a pass/fail question disqualify my tender?
Will I find out why I lost?
Where can you check the evidence?
Read the primary publication and the buyer’s current documents before acting.
| Source | What it supports |
|---|---|
| Procurement Act 2023, section 19 · legislation.gov.uk ↗ | Award and the most advantageous tender; read 25 October 2026. |
| Procurement Act 2023, section 23 · legislation.gov.uk ↗ | Award criteria and assessment methodology. |
| Procurement Act 2023, section 22 · legislation.gov.uk ↗ | Conditions of participation. |
| Procurement Act 2023, section 50 · legislation.gov.uk ↗ | Assessment summaries. |